What began as a plan to demolish a significant portion of the former Fairmount-Harford High School became an opportunity to preserve and transform the existing building. Through a design-build method, Southway developed an alternative approach that replaced extensive demolition with a comprehensive gut renovation, reducing costs while preserving the 127,000-sq-ft structure. The revised plan required only a 15,000-sq-ft addition to accommodate a new full-sized gymnasium.

Southway secured an early demolition permit to begin abatement and select demolition ahead of the full building permit to help maintain the fast-track schedule. The completed facility features a new first-floor kitchen and dining area, redesigned media center and common spaces, full-sized gymnasium and support spaces, and building systems upgraded to current codes and standards. Extensive site improvements included new hardscapes, cascading stairs, utilities, and stormwater management facilities, all carefully coordinated around a six-foot diameter water running through the site.

Project Type
K-12 Education
Client

Maryland Stadium Authority

Year Completed

2019

Value

$50,163,016

Surface Area

127,000 SF

Related Projects

K-12 Education

Explore More of our Projects by Sector